New Central Plant Installation Project

Scope of Work

We’re delivering the full mechanical electrical and controls scope for a new central plant at Troode Street, West Perth, for an undisclosed client. The work covers power cabling and controls for new chillers, cooling towers and pumps, along with a new mechanical services switchboard (MSSB). New DDC controls across the plant and air handling units are also in our scope, delivered alongside Icon Logic.

Project Details

Starting with the Switchboard 

The new MSSB comes first on the electrical side. All of the new plant and its controls take their supply from this board. 

 

Everything downstream depends on it, so circuit allocation and protection need to be settled before any cable goes in. 

 

Running Power to the New Plant 

Chillers are typically the largest loads in a central plant, so their supply cabling needs the most planning. Routes have to suit the plant layout and leave the mechanical trades room to install and maintain their equipment. 

 

The towers and pumps follow the same approach on a smaller scale. 

 

New DDC for the Plant and Air Handling Units 

The new DDC runs across both the central plant and the air handling units (AHUs). The AHUs need to work properly with the central plant for the building to respond to changing load. 

 

Our part is installing and terminating the field wiring the controls depend on. 

 

Coordinating with Icon Logic 

Icon Logic is working with us on the controls upgrade across the whole plant. What they need from us is wiring that’s correctly labelled and matches the documentation. 

 

Project Challenges and Solutions 

Fitting the Electrical Work Around Plant Deliveries 

Central plant equipment usually arrives and gets set in place in stages. At each step, the electrical program sits behind the mechanical one. 

 

Where we can, we’re getting containment and board work in ahead of each delivery. Final terminations wait until each item is in position. 

 

Getting the Controls Handover Right 

Faults in controls wiring are slow to find once programming starts, because they can look like software problems. That costs time for both teams. 

 

Our plan is to test each point before it goes across to Icon Logic. If something misbehaves during commissioning, the wiring can then be ruled out quickly. 

 

Client Feedback 

Works are still underway at Troode Street, so there’s no client feedback yet. When complete, the building will have new central plant equipment running under new DDC control. 