08 Dec CEX Meekatharra DB Upgrade
DB upgrade in the coles express service station. Upgraded the DB without affecting the fuel stations trading. Only use the cleaner photos. ...
DB upgrade in the coles express service station. Upgraded the DB without affecting the fuel stations trading. Only use the cleaner photos. ...
Upgraded and replaced the controls system for the refrigeration and mechanical systems. We did this all while keeping the refrigeration systems running, as Dnata catering servers the Perth Airport. ...
BMS Control Panel Design and Manufacture A dedicated BMS control panel was designed and manufactured in house to suit ALS operational requirements. The bright orange panel provides clear identification, clean internal layout and allowance for future expansion. Components, wiring and terminations were selected and assembled to meet...
Temporary Power Design and Generator Setup MECS supplied and positioned two backup generators to support refrigeration, lighting and essential store systems. Load assessments were completed to confirm capacity and distribution, and temporary power arrangements were designed to align with site operations, safety standards and Western Power...
This one was on a very tight time schedule, after a water leak inside the building knocked out 2 x MSSB’s serving the main plant room. MECS where engaged to build (Design & Manufacturer) the new MSSB’s, install them onsite and recommission the controls along...
This one was on a very tight time schedule, after a water leak inside the building knocked out 2 x MSSB’s serving the main plant room. MECS where engaged to build (Design & Manufacturer) the new MSSB’s, install them onsite and recommission the controls along...
Decommissioning and Controls Upgrade The project began with safe isolation and strip-out of the old plant and control gear. The tired infrastructure was removed, making way for the new MSSB and controls system that would provide reliable operation for the upgraded chiller and pump arrangement. Installation and...
Design and Separation To ensure compliance, MECS designed the layout so that all electrical control cabinets were installed in a dedicated service room. This separation provided a clear barrier between live electrical equipment and the compressor space, minimising the risk of ignition from flammable vapours. Fire Sealing...
Execution Strategy Installation and Wiring Positioned the switchboard within a confined plant room, coordinating lift access and clearances. Completed all terminations for pumps, fans, and control circuits, integrating with existing site infrastructure. Applied stainless‑steel fabrication and corrosion‑resistant fittings to suit the coastal environment. Testing and Commissioning Performed insulation, continuity, and functional...
Execution Strategy: Pre-Construction & Planning Collaborated with builders and refrigeration contractors to coordinate timing, site access and infrastructure requirements. Scoped electrical load demands for expanded display cases and back-of-house chillers. Planned staged shutdowns to avoid disruption to surrounding tenancies and minimise downtime. Fitout and Installation Supplied and installed submains, final circuits...