Upgraded and replaced the controls system for the refrigeration and mechanical systems. We did this all while keeping the refrigeration systems running, as Dnata catering servers the Perth Airport. ...

BMS Control Panel Design and Manufacture A dedicated BMS control panel was designed and manufactured in house to suit ALS operational requirements. The bright orange panel provides clear identification, clean internal layout and allowance for future expansion. Components, wiring and terminations were selected and assembled to meet...

Temporary Power Design and Generator Setup  MECS supplied and positioned two backup generators to support refrigeration, lighting and essential store systems. Load assessments were completed to confirm capacity and distribution, and temporary power arrangements were designed to align with site operations, safety standards and Western Power...

Temperzone PAC Replacement and New Control Panel We started by planning the changeover around live equipment. You cannot just pull gear out and hope for the best in an exchange. We supplied and installed new Temperzone PAC units sized for the room and load, then built a...

This one was on a very tight time schedule, after a water leak inside the building knocked out 2 x MSSB’s serving the main plant room. MECS where engaged to build (Design & Manufacturer) the new MSSB’s, install them onsite and recommission the controls along...

This one was on a very tight time schedule, after a water leak inside the building knocked out 2 x MSSB’s serving the main plant room. MECS where engaged to build (Design & Manufacturer) the new MSSB’s, install them onsite and recommission the controls along...

We were engaged direct by Coles to be the Principal Contractor on site and engage sub coontractors for building works. Our scope included all new switchboards to replace the various switchboards spread all over the store. We installed into an existing room which was to...

Clearing the Room  Asbestos isn’t something you muck around with. We called in PCB Contractors and Morgan Environmental, crews we’ve worked with before and trust. They came in, tested everything, sealed it up, and carefully stripped the sheeting out. Once they gave us the all-clear, we...